Timeline Phases
The Pontiac Economic Development Organizational (EDO) Framework Initiative will occur over an 18-month project timeline, divided into seven phases, which began in January 2026.
1
Complete
Project & Communication Management
January - March 2026
2
In Progress
Stakeholder Engagement & Framework Exploration
April - June 2026
3
Upcoming
Capacity Assessment & Call to Action
July - August 2026
4
Upcoming
Strategic Planning
September - October 2026
5
Upcoming
Legal Structuring
October - November 2026
6
Upcoming
Action Plan
December 2026 - February 2027
7
Upcoming
Initial Implementation
February - June 2027